Scenario

Hydro power plant

Nameplate data of transformer:

Transformer: power transformer
Year: 1948
Power [MVA]: 33
Voltage [KV]: 225
Oil mass [Kg]: 74.000 

Solution Sea Marconi

Solution: Dehydration treatment performed on-load (transformer fully load during the treatment)

Before the treatment

After the treatment

After 6 months

Oil temp. [°C] 15 63 35
Dissolved water [mg/Kg] IEC 60814 28 8 14
Saturation pecentage 62% 3% 13,94%
Water inside the paper using the equilibrium curve > 10% (*) 3,9%
Insulating condition IEC 60422 Extremely wet (*) Moderately wet
Breakdown voltagea [KV] IEC 60156 39,8 > 75 > 75

Problemas críticos identificados


Soluciones aplicadas

Contáctenos para conocer más sobre su caso






He leido la informaciòn y autorizo el procesaimento de mi datos personal pera los fines allì indicados.
Insert this code: captcha







Ho letto l'informativa e autorizzo il trattamento dei miei dati personali per le finalità ivi indicate.
Inserisci questo codice: captcha






I read the privacy information and authorize the use of my personal data for the purposes specified therein.
Insert this code: captcha







J'ai lu les informations et j'autorise le traitement de mes informations personnelles aux fins indiquées.
Entrez ce code: captcha






He leido la informaciòn y autorizo el procesaimento de mi datos personal pera los fines allì indicados.
Insert this code: captcha






I read the privacy information and authorize the use of my personal data for the purposes specified therein.
Insert this code: captcha