Situation

A global leader in the energy sector

Technical specifications of transformer:

Manufacturer: xxx
Year: 2013 (new)
Power [MVA]: 185
Voltage [kV]: 380/150
Oil mass [kg]: 50.940

Problem

Transformer empty following transport to destination site.

Solution

Estratto del rapporto di prova con esiti analitici dell’olio a fine intervento

Sea Marconi implemented the following measures: Filling the transformer under vacuum and oil treatment

Details of stages in the procedure

connecting and preparing the transformer for vacuum (1 day)
applying the vacuum to the transformer (3 days)
filling under vacuum (2 days)
checking the conservator and purging
treating the oil by circulating it through the Sea Marconi decontamination unit (two and a half days)
sampling the oil for testing at the end of process
disconnecting and uninstalling the site
Total duration of the process: 8 days

This treatment was carried out by Sea Marconi in conjunction with the manufacturer of the transformer who installed the transformer at the destination site and assembled the accessories.

Problemas críticos identificados


Soluções aplicadas

Entre em contato conosco para saber mais sobre o seu caso





    Li a informação de privacidade e autorizo o uso dos meus dados pessoais para os fins especificados ali.
    Inserir este código: captcha

    Não encontrou o que estava procurando?

    Entre em contato conosco para saber mais sobre o seu caso





      Li a informação de privacidade e autorizo o uso dos meus dados pessoais para os fins especificados ali.
      Inserir este código: captcha